2017 Projects:
- Weed Abatement
- Contractor: All Green Landscaping
- Cost: $4,613
- Completed: April 2017
- Ditch Cleaning and Shaping
- Contractor: Joe Vicini, Inc.
- Scope of Work: Clean and shape selected ditch areas on Crystal Blvd, Manganite, Dolomite and Galena
- Cost: $18,737
- Completed: May 2017
- South Crystal Petromat Overlay and Chip Seal
- Contractor: Veerkamp General Engineering
- Scope of Work: Complete installation of engineered fabric and double chip seal overlay on Crystal Blvd between Mica and S. end of Crystal.
- Cost: $102,022
- Completed: September 2017
- Galena Chip Seal
- Contractor: Veerkamp General Engineering
- Scope of Work: Apply a single layer chip seal on Galena between the turnaround and Dolomite
- Cost: $11,000
- Completed: September 2017
- Asphalt Repair on Crystal Blvd.
- Contractor: Veerkamp General Engineering
- Scope of Work: Repair and replace asphalt near 7800 Crystal Blvd. plus added a/c work
- Cost: $11,000
- Completed: September 2017
- Asphalt Repair on Crystal Blvd.
- Contractor: Veerkamp General Engineering
- Scope of Work: Apply skin patch and double chip seal to several locations on Crystal Blvd.
- Cost: $17,000
- Completed: September 2017
- North Crystal Chip Seal
- Contractor: Veerkamp General Engineering
- Scope of Work: Apply single coat chip seal to Crystal Blvd. between Ferrite and Obrizo
- Cost: $31,000
- Completed: September 2017
- Galena Striping and Marking
- Contractor: Sierra Traffic Markings Inc
- Scope of Work: Centerline, fog line and misc markings on Crystal and Galena
- Cost: $9,450
- Completed: September 2017